How to debug the newly purchased diesel generator set?
How to debug the newly purchased diesel generator set?
Sep 30, 2022
Share:
After the diesel generator set is installed, it needs to be debugged before it can be put into normal use. Of course, the generator set has been strictly tested before leaving the factory. The following generator set manufacturer Shandong Huali Electromechanical will introduce to you how to debug the newly purchased diesel generator set.
1. After closing the insurance in the generator set control box, press the start button and press the button three or four times. If the start is unsuccessful, wait for about half a minute to start again. If the repeated operation fails to start, the start operation should be stopped. Check whether the battery voltage or oil circuit is a fault factor, and restart it after removing it.

2. After the generator set is started, check the parameters of the control box module, oil pressure, water temperature, voltage, frequency, etc.

3. After the generator set is started, the speed directly reaches the rated speed. For the generator set with idle speed requirements, the idle speed time is generally 3~5min, and the idle speed time is not too long, otherwise the related components of the generator may be burned out.

4. Check the fastening of each connection of the unit to see if there is looseness and severe vibration, and check the leakage of the oil circuit, water circuit and electrical appliances of the unit. .

5. Observe whether the various protection and monitoring devices of the unit are normal.

6. When the speed reaches the rated speed and the parameters of no-load operation are stable, switch on and power on.

7. Carry out necessary debugging knowledge training for operators.

If you want to know more about the debugging of diesel generator sets, please consult Shandong Huali Electromechanical Co., Ltd., the source factory of the generator set.